ROY HILL
We are on schedule with the first fix (wiring
of) the signature buildings. The switchboards and fittings will be onsite as of
next week, ready for us to commence the second fix.The main schedule
dates are on target within the buildings engaged and the fire protection sub-contractor
switchboard delivery is also on target.
Progress of the administration building at Roy Hill. |
Administration Building Activities:
- Installation of Power Outlets
Auditorium Building Activities:
- Installation of Light and Power Cable runs
- Installation of AV Conduit runs within the Auditorium Main Theatre
Dry Mess Building Activities:
- Installation of Kitchen Lights
- Installation of Power Cables
- Installation of 32mm Flexi Conduit
- Installation of Power Cables through Kingspan to MSSB
Wet Mess Building Activities:
- Installation of Lighting and Small Cabling
MUNDARING WATER TREATMENT PLANT
The
HV 22kV power is now on at the main plant. Lighting, small power distribution
boards and control cabinets are being pre-commissioned in the 19 individual
buildings. This will allow Brookfield Multiplex and ATJV to test and approve
the process. As the contract is demobilising, the construction phase is de-manning and pre-commissioning phase is
manning up. Then onto the final phase of commissioning before producing the
final product.
Tomorrow’s Daily Work Activities:
Blower & Compressor:
- Small light & power install
- Install Perspex on 630mm incomers
- Fit off and terminate pressurization pumps
- Fit cable tags
DAFF:
- Fit off level instruments and complete suncover
Chlorine Building:
LV2:
- Cables terminations
BAC:
- Fit off rotork valves
- Terminate pressurization pumps
- Carry out punch list items
Operations:
- Analyzer
- UPS system termination
- Terminations
- Punch list items
Service water:
- Hand over ITR package
- Redline drawings
RED GULLY
As of early this month,
Red Gully is producing product (gas). It was a successful contract for
all involved.
PYRENEES FPSO
LOGIC
are doing small maintenance and upgrade work for the vessel owners offshore on
the Pyrenees. This type of Contract is particularly difficult for the following
reasons:
- Live offshore production oil rig
- OHS is a critical path
- Planning must be very precise regarding sequence shut down timing, as over-run of shut would be seen as loss of production
- Planning must be very precise regarding material and equipment as when you are on the shut, if there is any missing material and/or equipment it would be seen as loss of production
No comments:
Post a Comment